The Federal Executive Council, FEC, yesterday, May 14, approved the procurement of critical equipment to improve the electricity sector.
This was revealed by the Minister of Power, Adelabu after the Council’s meeting. He pointed that the three memoranda presented by his ministry to the Council got approval.
Explaining the breakdown of the approvals, Adelabu stated that the first is for the procurement of 10 transformers and 10 reactors for the Transmission Company of Nigeria, TCN, at $4.8 million and N102 million.
According to him, this would enhance the optimal performance of the national grid. And will also reduce the risk of electrical shock and equipment damage and protect personnel from the effects of high voltage.
The second approval, the Minister said, is for the construction of a 93-kilometre transmission line at Oji River/9th Mile, Enugu State. He said the 132 KV double circuit transmission line is valued at $33.9 million and N10.1 million.
He posited that the project when operational will stabilize the national grid and expand its capacity. This is in line with the national grid expansion plan and the Presidential Power Initiative to increase the end-to-end capacity of the national grid.
According to him, the third approval is for the supply and installation of 15 units of emergency restoration systems for 330 KV and 132 KV transmission lines. He said, this will enable the quick fixing of vandalized and damaged power infrastructure, valued at $14 million.
The Minister stated that the procurement is a response to the impact of vandalism on power transmission assets. Particularly in the Northeast, where there has been a two-week blackout due to vandalism.
He said, “The Transmission Company of Nigeria (TCN) is working to fix the vandalized assets. And to restore normalcy to the region by the end of the month.
“The emergency restoration system will ensure 24/7 uninterrupted power supply. And the Government is committed to ensuring the stability, sustainability, and cost-effectiveness of power supply. As well as planning for future growth.
“Overall, these approvals demonstrate the Government’s commitment to addressing the challenges in the power sector. And also, to provide reliable power to citizens, which is critical for economic growth and development,” the Minister stated.